Empanelled with MoRTH under
Category IV : GeoTechnical Investigation
RITES Limited
Complete Project

1. Geotechnical Investigation for Rail based Mass Transit system in Kanpur Metro Rail Corporation Limited. (Uttar Pradesh)

Project Type: Sub-Soil Investigation

Contract Value: 9,72,420.00

Project Detail
Geotechnical Investigation for Rail based Mass Transit system in Kanpur Metro Rail Corporation Limited. (Uttar Pradesh)

Authority Under Whom Executed
To, Joint General Manager/GT, RITES Ltd,
RITES Bhawan, No. 1, Sector-29, Gurgaon-122001

Time Taken: 2 Month

Remarks:All field activities, conducting SPT collection of DS & UDS including lab test and submission of test report along with recommendation for safe bearing capacity at various depths. Kanpur Metro Rail Corporation Limited. (Uttar Pradesh)

2. Geo Technical Investigation Work For The Proposed Lingaraj Silo Connectivity With NTPC captive Line At Talcher coalfields

Project Type: Sub-Soil Investigation

Contract Value: 10,85,875.00

Project Detail
Geo Technical Investigation Work For The Proposed Lingaraj Silo Connectivity With NTPC captive Line At Talcher coalfields

Authority Under Whom Executed
To, Jt. General Manager, RITES Ltd;
Bhagwan Tower, 1st’ Floor, Block-A, Cuttack Road, Bhubaneswar- 751 006

Time Taken: 3 Month

Remarks:Drilling of PX size borehole in all types of Soils. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131. Drilling of NX/NQ size borehole in all types of rock and boulder strata including lab test and submission of test report along with recommendation for safe bearing capacity at various depths.

3. Geotechnical Investigation work for preparation of ‘Detailed Project Report (DPR) for removing bottleneck points of Kona Expressway by constructing new ROB/RUB, flyovers and integrated Traffic Circulation Plan for Santragachi railway Station and Santragachi Bus Terminus from Kona Expressway

Project Type: Sub-Soil Investigation

Contract Value: 23,75,570.00

Project Detail
Geotechnical Investigation work for preparation of ‘Detailed Project Report (DPR) for removing bottleneck points of Kona Expressway by constructing new ROB/RUB, flyovers and integrated Traffic Circulation Plan for Santragachi railway Station and Santragachi Bus Terminus from Kona Expressway.

Authority Under Whom Executed
To, The DGM (HW)
RITES Ltd, Highway Division, Kolkata Metro Railway Service Building, (4th Floor)56, C.R. Avenue, Kolkata-700012

Time Taken: 2 Month

Remarks:All field activities, conducting SPT collection of DS & UDS including lab test and submission of test report along with recommendation for safe bearing capacity at various depths.

4. Geo-Technical Investigation in Proposed Viaduct & ROB locations in connection with the work of PMC Services for Development of New Railway Siding Near Gua Railway Station, Gua Iron Mines of SAIL, RMD Dist. West Singbhum, Jharkhand.

Project Type: Sub-Soil Investigation

Contract Value: 10,76,012.50

Project Detail
Geo-Technical Investigation in Proposed Viaduct & ROB locations in connection with the work of PMC Services for Development of New Railway Siding Near Gua Railway Station, Gua Iron Mines of SAIL, RMD Dist. West Singbhum, Jharkhand.

Authority Under Whom Executed
To The Joint General Manager/GT,
RITES Limited, RITES Bhawan No. 1, Sector-29, Gurgaon, Haryana

Time Taken: 2 Month

Remarks:Drilling of PX size borehole in all types of Soils. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131. Drilling of NX/NQ size borehole in all types of rock and boulder strata including lab test and submission of test report along with recommendation for safe bearing capacity at various depths.

5. Geo-Technical Investigation for the work for 9 ROB's of Bhaupur-Khurja Section of EDFC.

Project Type: Sub-Soil Investigation

Contract Value: 27,55,300.00

Project Detail
Geo-Technical Investigation for the work for 9 ROB's of Bhaupur-Khurja Section of EDFC.

Authority Under Whom Executed
To The Joint General Manager/GT,
RITES Limited, RITES Bhawan No. 1, Sector-29, Gurgaon, Haryana

Time Taken: 3 Month

Remarks:Drilling of PX size borehole in all types of Soils. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131.

6. Geo-Technical Investigation for the work for 5 ROB's on Khurja - Dadri Section of EDFC.

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geo-Technical Investigation for the work for 5 ROB's on Khurja - Dadri Section of EDFC.

Authority Under Whom Executed
Joint General Manager/GT,
RITES Limited, RITES Bhawan No. 1, Sector-29, Gurgaon, Haryana

Time Taken: 60 Days

Remarks: Drilling of PX size borehole in all types of Soils. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131.

7. Geotechnical Investigation work in different location of Bridges and deep cutting of formation for setting up Rail Infrastructure work of proposed siding of Amrapali OCP of CCP Jharkhand.

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geotechnical Investigation work in different location of Bridges and deep cutting of formation for setting up Rail Infrastructure work of proposed siding of Amrapali OCP of CCP Jharkhand.

Authority Under Whom Executed
GM (Projects)
RITES Limited, Regional Project office, 2nd Floor, Metro Railway Service Building, 56, C.R. Avenue, Kolkata-700 012

Time Taken: 90 Days

Remarks: Drilling of NX/NQ size borehole in all types of rock and boulder strata including lab test and submission of test report along with recommendation for safe bearing capacity at various depths.

8. Geotechnical Investigation for extension of corridor from Gurgaon railway station to old Delhi road near sector-22

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geotechnical Investigation for extension of corridor from Gurgaon railway station to old Delhi road near sector-22

Authority Under Whom Executed
Dy. General Manager /GT,
RITES Ltd, RITES Bhawan, Plot No. 01, Sector-29, Gurgaon, Haryana-122001

Time Taken: 30 Days

Remarks: Drilling of PX size borehole in all types of Soils. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131.

9. Geotechnical Investigation for NUPPL Siding at Ghatampur with takeoff from Hamirpur Road Railway Station.

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geotechnical Investigation for NUPPL Siding at Ghatampur with takeoff from Hamirpur Road Railway Station.

Authority Under Whom Executed
RITES Limited
RITES Bhawan, No. 1, Sector-29, Gurgaon, Haryana.

Time Taken: 1 Month

Remarks: Drilling of PX size borehole in all types of Soils. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131.

10. Geotechnical Investigation for Nasik Metro. (MRTS)

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geotechnical Investigation for Nasik Metro. (MRTS)

Authority Under Whom Executed
The JGM/GT
RITES Ltd, Rites Bhawan, Plot No. 1, Sector-29, Gurgaon.

Time Taken: 75 Days

Remarks: Drilling of NX/NQ size borehole in all types of Soils/Rock. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131.

11. Geotechnical Investigation for additional work for Consultancy Services for 5 ROB's on Khurja-Dadri Section of EDFCCIL.

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geotechnical Investigation for additional work for Consultancy Services for 5 ROB's on Khurja-Dadri Section of EDFCCIL.

Authority Under Whom Executed
The JGM/GT
RITES Ltd, Rites Bhawan, Plot No. 1, Sector-29, Gurgaon.

Time Taken: 30 Days

Remarks:Drilling of NX/NQ size borehole in all types of Soils/Rock. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131.

12. Geotechnical Investigation for preparation of DPR for Metro Rail Connection from Rezangla chowk, Gurgaon to Sector-24, Dwarka.

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geotechnical Investigation for preparation of DPR for Metro Rail Connection from Rezangla chowk, Gurgaon to Sector-24, Dwarka.

Authority Under Whom Executed
The JGM/GT
RITES Ltd, Rites Bhawan, Plot No. 1, Sector-29, Gurgaon.

Time Taken: 2 Month

Remarks: Drilling of NX/NQ size borehole in all types of Soils/Rock. Collection of disturbed/ undisturbed soil samples and water sample. Conducting Standard Penetration test as per IS: 2131.

13. Conducting of Preliminary Survey and Preparation of Land Plan & Land Schedule making Pillars for Construction of Necessary Railway Infrastructure for Proposed transportation of coal by WBPDCL its Power Plants to be mined from Panchwara (North), Jharkhand.

Project Type: Topographical Survey

Contract Value:

Project Detail
Conducting of Preliminary Survey and Preparation of Land Plan & Land Schedule making Pillars for Construction of Necessary Railway Infrastructure for Proposed transportation of coal by WBPDCL its Power Plants to be mined from Panchwara (North), Jharkhand.

Authority Under Whom Executed
The General Manager (Projects)
RITES Limited, Regional Project office, 56, C.R. Avenue, 2nd Floor, K

Time Taken:

Remarks:Preliminary Engineering Survey with Total Station instrument (1 second accuracy with calibrated) including traversing along the proposed alignment, taking details of 200 m corridor existing topographical features such as bridge including HFL, roads, rivers nallas, canals, waterways, buildings village boundary, boundary wall, overhead power line with posts/ towers, communication line with posts/towers etc.

14. Geotechnical Investigation for the proposed Rail Flyovers (RFO) near Pt. Deen Dayal Upadhyay Stations in connection with construction of Eastern Dedicated Freight Corridor.

Project Type: Sub-Soil Investigation

Contract Value:

Project Detail
Geotechnical Investigation for the proposed Rail Flyovers (RFO) near Pt. Deen Dayal Upadhyay Stations in connection with construction of Eastern Dedicated Freight Corridor.

Authority Under Whom Executed
RITES Limited
RITES Bhawan, Plot No. 1, Sec-29, Gurgaon, Haryana-122 001

Time Taken: 3 Month

Remarks: All field activities as per BOQ, lab test and submission of test report along with recommendation for safe bearing capacity at various depths.

Clients