Project Detail
Vertical load testing of test piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/ Reaction augers, installation of measuring instrument, preparation of pile head, conducting the vertical pile load test and submission of test report but excluding excavation of pit up to the cut-off level of pile and cutting of cut-off length of pile. complete as per specification. Initial load test up to 300 tonnes (Test Load 2.5 times the Safe/ design capacity ie. 120T).
Authority Under Whom Executed
H.G. Infra Engineering Limited
14,PANCHWATI COLONY,RATANADA,JODHPUR 342001,Rajasthan(India)
Time Taken: 1 month
Remarks:“The scope of work comprising Initial Vertical Load Testing of test piles up to 300 tonnes (2.5 × design capacity of 120 T), conforming to IS 2911 (Part IV), was executed with full compliance to the prescribed standards and project specifications. The testing operations included installation of the Kentledge/Reaction system, construction of a stable loading platform, precise alignment and preparation of the pile head, deployment and calibration of displacement measuring instruments (dial gauges/ LVDTs), staged load application as per the loading sequence, and continuous monitoring of settlements under incremental and sustained loads. All field observations and results were systematically recorded, analyzed, and compiled in a comprehensive test report.
The assignment awarded by H.G. Infra Engineering Limited on 05.01.2024 was completed on 04.02.2024 within the defined timeline, ensuring adherence to safety protocols, methodological accuracy, and quality assurance requirements.”
If you want it even more detailed with specific testing sequence, instrumentation type, settlement criteria, or references to IS clauses, I can add that too.